Sensim Math · Depth 한국어

← 4-2 · Fill a table and complete a line graph from clues · Solve a Table or Graph Step by Step from Clues

Fill a table and complete a line graph from clues · 8 practice problems

4.OA.A.35.MD.B.2

Generated variants — 8

Freshly produced from the archetype’s parameters — problem, figure, and solution derived together.

Variant 1 answer: June = 200 books, July = 300 books

The line graph shows the books sold recorded each month. In June the count was 4040 more than in May, and the number in June and July together is 500500. Complete the line graph.

(Figure) A line graph titled "Books Sold." The horizontal axis shows the month - 33 (March), 44 (April), 55 (May), 66 (June), 77 (July). The vertical axis shows the number of books, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 books. Points are plotted and joined for March at 120120; April at 220220; May at 160160; the points for June and July have not yet been plotted.

Books Sold 0 100 200 300 400 (books) 3 4 5 6 7 Month
Show solution

Understand

A line graph of books sold each month shows March = 120, April = 220, May = 160; June and July are blank. June is 40 more than May, and June + July together is 500. I must find the June and July counts to complete the graph.

Givens
  • March = 120 books, April = 220 books, May = 160 books
  • June = May + 40
  • June + July = 500
  • Each small grid square = 20 books
Unknowns
  • Number of books made in June
  • Number of books made in July
Constraints
  • Plotted June and July values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first June (May plus 40), then July (the 500 total minus June). Each is a one-step subproblem, and finding July uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
June is 40 more than May, and May is 160, so June = 160 + 40 = 200.
160+40=200160 + 40 = 200
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
June and July together make 500, so July = 500 - June = 500 - 200 = 300.
500200=300500 - 200 = 300
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), June 200 sits 0 squares above 200, and July 300 sits 0 squares above 300; join the points with straight segments.
200=200+0×20,300=300+0×20200 = 200 + 0\times 20,\quad 300 = 300 + 0\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: June = 200 books, July = 300 books

Review

Check the clues: June 200 is indeed 40 more than May 160, and June 200 + July 300 = 500 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let June = J = 160 + 40 and July = 500 - J; solving gives the same J = 200 and July = 300.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing June from May and July from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the June and July values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 2 answer: July = 260 frames, August = 380 frames

The line graph shows the picture frames made recorded each month. In July the count was 8080 more than in June, and the number in July and August together is 640640. Complete the line graph.

(Figure) A line graph titled "Picture Frames Made." The horizontal axis shows the month - 44 (April), 55 (May), 66 (June), 77 (July), 88 (August). The vertical axis shows the number of frames, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 frames. Points are plotted and joined for April at 280280; May at 380380; June at 180180; the points for July and August have not yet been plotted.

Picture Frames Made 0 100 200 300 400 (frames) 4 5 6 7 8 Month
Show solution

Understand

A line graph of picture frames made each month shows April = 280, May = 380, June = 180; July and August are blank. July is 80 more than June, and July + August together is 640. I must find the July and August counts to complete the graph.

Givens
  • April = 280 frames, May = 380 frames, June = 180 frames
  • July = June + 80
  • July + August = 640
  • Each small grid square = 20 frames
Unknowns
  • Number of frames made in July
  • Number of frames made in August
Constraints
  • Plotted July and August values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first July (June plus 80), then August (the 640 total minus July). Each is a one-step subproblem, and finding August uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
July is 80 more than June, and June is 180, so July = 180 + 80 = 260.
180+80=260180 + 80 = 260
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
July and August together make 640, so August = 640 - July = 640 - 260 = 380.
640260=380640 - 260 = 380
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), July 260 sits 3 squares above 200, and August 380 sits 4 squares above 300; join the points with straight segments.
260=200+3×20,380=300+4×20260 = 200 + 3\times 20,\quad 380 = 300 + 4\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: July = 260 frames, August = 380 frames

Review

Check the clues: July 260 is indeed 80 more than June 180, and July 260 + August 380 = 640 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let July = J = 180 + 80 and August = 640 - J; solving gives the same J = 260 and August = 380.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing July from June and August from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the July and August values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 3 answer: Week 4 = 300 cars, Week 5 = 400 cars

The line graph shows the toy cars made recorded each week. In Week 4 the count was 6060 more than in Week 3, and the number in Week 4 and Week 5 together is 700700. Complete the line graph.

(Figure) A line graph titled "Toy Cars Made." The horizontal axis shows the week - 11 (Week 1), 22 (Week 2), 33 (Week 3), 44 (Week 4), 55 (Week 5). The vertical axis shows the number of cars, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 cars. Points are plotted and joined for Week 1 at 200200; Week 2 at 300300; Week 3 at 240240; the points for Week 4 and Week 5 have not yet been plotted.

Toy Cars Made 0 100 200 300 400 (cars) 1 2 3 4 5 Week
Show solution

Understand

A line graph of toy cars made each week shows Week 1 = 200, Week 2 = 300, Week 3 = 240; Week 4 and Week 5 are blank. Week 4 is 60 more than Week 3, and Week 4 + Week 5 together is 700. I must find the Week 4 and Week 5 counts to complete the graph.

Givens
  • Week 1 = 200 cars, Week 2 = 300 cars, Week 3 = 240 cars
  • Week 4 = Week 3 + 60
  • Week 4 + Week 5 = 700
  • Each small grid square = 20 cars
Unknowns
  • Number of cars made in Week 4
  • Number of cars made in Week 5
Constraints
  • Plotted Week 4 and Week 5 values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first Week 4 (Week 3 plus 60), then Week 5 (the 700 total minus Week 4). Each is a one-step subproblem, and finding Week 5 uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
Week 4 is 60 more than Week 3, and Week 3 is 240, so Week 4 = 240 + 60 = 300.
240+60=300240 + 60 = 300
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
Week 4 and Week 5 together make 700, so Week 5 = 700 - Week 4 = 700 - 300 = 400.
700300=400700 - 300 = 400
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), Week 4 300 sits 0 squares above 300, and Week 5 400 sits 0 squares above 400; join the points with straight segments.
300=300+0×20,400=400+0×20300 = 300 + 0\times 20,\quad 400 = 400 + 0\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: Week 4 = 300 cars, Week 5 = 400 cars

Review

Check the clues: Week 4 300 is indeed 60 more than Week 3 240, and Week 4 300 + Week 5 400 = 700 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let Week 4 = J = 240 + 60 and Week 5 = 700 - J; solving gives the same J = 300 and Week 5 = 400.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing Week 4 from Week 3 and Week 5 from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the Week 4 and Week 5 values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 4 answer: July = 300 tickets, August = 300 tickets

The line graph shows the tickets sold recorded each month. In July the count was 8080 more than in June, and the number in July and August together is 600600. Complete the line graph.

(Figure) A line graph titled "Tickets Sold." The horizontal axis shows the month - 44 (April), 55 (May), 66 (June), 77 (July), 88 (August). The vertical axis shows the number of tickets, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 tickets. Points are plotted and joined for April at 240240; May at 340340; June at 220220; the points for July and August have not yet been plotted.

Tickets Sold 0 100 200 300 400 (tickets) 4 5 6 7 8 Month
Show solution

Understand

A line graph of tickets sold each month shows April = 240, May = 340, June = 220; July and August are blank. July is 80 more than June, and July + August together is 600. I must find the July and August counts to complete the graph.

Givens
  • April = 240 tickets, May = 340 tickets, June = 220 tickets
  • July = June + 80
  • July + August = 600
  • Each small grid square = 20 tickets
Unknowns
  • Number of tickets made in July
  • Number of tickets made in August
Constraints
  • Plotted July and August values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first July (June plus 80), then August (the 600 total minus July). Each is a one-step subproblem, and finding August uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
July is 80 more than June, and June is 220, so July = 220 + 80 = 300.
220+80=300220 + 80 = 300
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
July and August together make 600, so August = 600 - July = 600 - 300 = 300.
600300=300600 - 300 = 300
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), July 300 sits 0 squares above 300, and August 300 sits 0 squares above 300; join the points with straight segments.
300=300+0×20,300=300+0×20300 = 300 + 0\times 20,\quad 300 = 300 + 0\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: July = 300 tickets, August = 300 tickets

Review

Check the clues: July 300 is indeed 80 more than June 220, and July 300 + August 300 = 600 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let July = J = 220 + 80 and August = 600 - J; solving gives the same J = 300 and August = 300.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing July from June and August from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the July and August values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 5 answer: Day 4 = 200 loaves, Day 5 = 260 loaves

The line graph shows the loaves baked recorded each day. In Day 4 the count was 6060 more than in Day 3, and the number in Day 4 and Day 5 together is 460460. Complete the line graph.

(Figure) A line graph titled "Loaves Baked." The horizontal axis shows the day - 11 (Day 1), 22 (Day 2), 33 (Day 3), 44 (Day 4), 55 (Day 5). The vertical axis shows the number of loaves, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 loaves. Points are plotted and joined for Day 1 at 180180; Day 2 at 280280; Day 3 at 140140; the points for Day 4 and Day 5 have not yet been plotted.

Loaves Baked 0 100 200 300 400 (loaves) 1 2 3 4 5 Day
Show solution

Understand

A line graph of loaves baked each day shows Day 1 = 180, Day 2 = 280, Day 3 = 140; Day 4 and Day 5 are blank. Day 4 is 60 more than Day 3, and Day 4 + Day 5 together is 460. I must find the Day 4 and Day 5 counts to complete the graph.

Givens
  • Day 1 = 180 loaves, Day 2 = 280 loaves, Day 3 = 140 loaves
  • Day 4 = Day 3 + 60
  • Day 4 + Day 5 = 460
  • Each small grid square = 20 loaves
Unknowns
  • Number of loaves made in Day 4
  • Number of loaves made in Day 5
Constraints
  • Plotted Day 4 and Day 5 values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first Day 4 (Day 3 plus 60), then Day 5 (the 460 total minus Day 4). Each is a one-step subproblem, and finding Day 5 uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
Day 4 is 60 more than Day 3, and Day 3 is 140, so Day 4 = 140 + 60 = 200.
140+60=200140 + 60 = 200
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
Day 4 and Day 5 together make 460, so Day 5 = 460 - Day 4 = 460 - 200 = 260.
460200=260460 - 200 = 260
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), Day 4 200 sits 0 squares above 200, and Day 5 260 sits 3 squares above 200; join the points with straight segments.
200=200+0×20,260=200+3×20200 = 200 + 0\times 20,\quad 260 = 200 + 3\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: Day 4 = 200 loaves, Day 5 = 260 loaves

Review

Check the clues: Day 4 200 is indeed 60 more than Day 3 140, and Day 4 200 + Day 5 260 = 460 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let Day 4 = J = 140 + 60 and Day 5 = 460 - J; solving gives the same J = 200 and Day 5 = 260.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing Day 4 from Day 3 and Day 5 from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the Day 4 and Day 5 values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 6 answer: Week 4 = 260 kites, Week 5 = 320 kites

The line graph shows the kites made recorded each week. In Week 4 the count was 8080 more than in Week 3, and the number in Week 4 and Week 5 together is 580580. Complete the line graph.

(Figure) A line graph titled "Kites Made." The horizontal axis shows the week - 11 (Week 1), 22 (Week 2), 33 (Week 3), 44 (Week 4), 55 (Week 5). The vertical axis shows the number of kites, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 kites. Points are plotted and joined for Week 1 at 140140; Week 2 at 240240; Week 3 at 180180; the points for Week 4 and Week 5 have not yet been plotted.

Kites Made 0 100 200 300 400 (kites) 1 2 3 4 5 Week
Show solution

Understand

A line graph of kites made each week shows Week 1 = 140, Week 2 = 240, Week 3 = 180; Week 4 and Week 5 are blank. Week 4 is 80 more than Week 3, and Week 4 + Week 5 together is 580. I must find the Week 4 and Week 5 counts to complete the graph.

Givens
  • Week 1 = 140 kites, Week 2 = 240 kites, Week 3 = 180 kites
  • Week 4 = Week 3 + 80
  • Week 4 + Week 5 = 580
  • Each small grid square = 20 kites
Unknowns
  • Number of kites made in Week 4
  • Number of kites made in Week 5
Constraints
  • Plotted Week 4 and Week 5 values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first Week 4 (Week 3 plus 80), then Week 5 (the 580 total minus Week 4). Each is a one-step subproblem, and finding Week 5 uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
Week 4 is 80 more than Week 3, and Week 3 is 180, so Week 4 = 180 + 80 = 260.
180+80=260180 + 80 = 260
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
Week 4 and Week 5 together make 580, so Week 5 = 580 - Week 4 = 580 - 260 = 320.
580260=320580 - 260 = 320
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), Week 4 260 sits 3 squares above 200, and Week 5 320 sits 1 squares above 300; join the points with straight segments.
260=200+3×20,320=300+1×20260 = 200 + 3\times 20,\quad 320 = 300 + 1\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: Week 4 = 260 kites, Week 5 = 320 kites

Review

Check the clues: Week 4 260 is indeed 80 more than Week 3 180, and Week 4 260 + Week 5 320 = 580 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let Week 4 = J = 180 + 80 and Week 5 = 580 - J; solving gives the same J = 260 and Week 5 = 320.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing Week 4 from Week 3 and Week 5 from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the Week 4 and Week 5 values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 7 answer: August = 300 cups, September = 380 cups

The line graph shows the cups sold recorded each month. In August the count was 4040 more than in July, and the number in August and September together is 680680. Complete the line graph.

(Figure) A line graph titled "Cups Sold." The horizontal axis shows the month - 55 (May), 66 (June), 77 (July), 88 (August), 99 (September). The vertical axis shows the number of cups, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 cups. Points are plotted and joined for May at 200200; June at 320320; July at 260260; the points for August and September have not yet been plotted.

Cups Sold 0 100 200 300 400 (cups) 5 6 7 8 9 Month
Show solution

Understand

A line graph of cups sold each month shows May = 200, June = 320, July = 260; August and September are blank. August is 40 more than July, and August + September together is 680. I must find the August and September counts to complete the graph.

Givens
  • May = 200 cups, June = 320 cups, July = 260 cups
  • August = July + 40
  • August + September = 680
  • Each small grid square = 20 cups
Unknowns
  • Number of cups made in August
  • Number of cups made in September
Constraints
  • Plotted August and September values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first August (July plus 40), then September (the 680 total minus August). Each is a one-step subproblem, and finding September uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
August is 40 more than July, and July is 260, so August = 260 + 40 = 300.
260+40=300260 + 40 = 300
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
August and September together make 680, so September = 680 - August = 680 - 300 = 380.
680300=380680 - 300 = 380
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), August 300 sits 0 squares above 300, and September 380 sits 4 squares above 300; join the points with straight segments.
300=300+0×20,380=300+4×20300 = 300 + 0\times 20,\quad 380 = 300 + 4\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: August = 300 cups, September = 380 cups

Review

Check the clues: August 300 is indeed 40 more than July 260, and August 300 + September 380 = 680 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let August = J = 260 + 40 and September = 680 - J; solving gives the same J = 300 and September = 380.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing August from July and September from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the August and September values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!
Variant 8 answer: Day 4 = 300 bottles, Day 5 = 340 bottles

The line graph shows the bottles filled recorded each day. In Day 4 the count was 100100 more than in Day 3, and the number in Day 4 and Day 5 together is 640640. Complete the line graph.

(Figure) A line graph titled "Bottles Filled." The horizontal axis shows the day - 11 (Day 1), 22 (Day 2), 33 (Day 3), 44 (Day 4), 55 (Day 5). The vertical axis shows the number of bottles, with major gridlines at 00, 100100, 200200, 300300, 400400 and each small grid square worth 2020 bottles. Points are plotted and joined for Day 1 at 160160; Day 2 at 260260; Day 3 at 200200; the points for Day 4 and Day 5 have not yet been plotted.

Bottles Filled 0 100 200 300 400 (bottles) 1 2 3 4 5 Day
Show solution

Understand

A line graph of bottles filled each day shows Day 1 = 160, Day 2 = 260, Day 3 = 200; Day 4 and Day 5 are blank. Day 4 is 100 more than Day 3, and Day 4 + Day 5 together is 640. I must find the Day 4 and Day 5 counts to complete the graph.

Givens
  • Day 1 = 160 bottles, Day 2 = 260 bottles, Day 3 = 200 bottles
  • Day 4 = Day 3 + 100
  • Day 4 + Day 5 = 640
  • Each small grid square = 20 bottles
Unknowns
  • Number of bottles made in Day 4
  • Number of bottles made in Day 5
Constraints
  • Plotted Day 4 and Day 5 values must land on grid squares worth 20 each

Plan

#7 Identify Subproblems · also uses: #11 Work Backwards

I solve in order from what I can already know: first Day 4 (Day 3 plus 100), then Day 5 (the 640 total minus Day 4). Each is a one-step subproblem, and finding Day 5 uses the total backwards.

Execute

#7 Identify Subproblems 4.OA.A.3
Day 4 is 100 more than Day 3, and Day 3 is 200, so Day 4 = 200 + 100 = 300.
200+100=300200 + 100 = 300
Start from the value you already know and apply the given step.
#11 Work Backwards 4.OA.A.3
Day 4 and Day 5 together make 640, so Day 5 = 640 - Day 4 = 640 - 300 = 340.
640300=340640 - 300 = 340
Knowing the total and one part, subtract to recover the other part.
#7 Identify Subproblems 5.MD.B.2
On the graph (each square = 20), Day 4 300 sits 0 squares above 300, and Day 5 340 sits 2 squares above 300; join the points with straight segments.
300=300+0×20,340=300+2×20300 = 300 + 0\times 20,\quad 340 = 300 + 2\times 20
Converting the numbers into squares lets you place each point exactly.
Answer: Day 4 = 300 bottles, Day 5 = 340 bottles

Review

Check the clues: Day 4 300 is indeed 100 more than Day 3 200, and Day 4 300 + Day 5 340 = 640 as required. Both values land neatly on grid lines (multiples of 20), so the plotted points are valid.

Convert to algebra (tool 13): let Day 4 = J = 200 + 100 and Day 5 = 640 - J; solving gives the same J = 300 and Day 5 = 340.

Standards · min grade 5

  • 4.OA.A.3 Solve multi-step word problems using four operations with whole numbers — Computing Day 4 from Day 3 and Day 5 from the total
  • 5.MD.B.2 Make a line plot to display a data set and solve problems using the data — Placing the Day 4 and Day 5 values on the scaled graph
💡 Fill in what you can figure out first, then use the total to get the rest - then just plot!